| Toledo Edison on Schedule to Complete Fulton Substation |
Located in
"This new substation demonstrates a continuing commitment to supporting load growth and enhancing reliability across our service area," said
The substation will provide additional voltage support to five substations on Toledo Edison's system, as well as five customer substations at large industrial operations in the area.
Construction on the Fulton Substation began in February. Contractors were used for all the underground and concrete work, and the rest of the construction is being completed by Toledo Edison employees. The transformer in this substation holds 12,600 gallons of mineral oil and will weigh almost 200 tons when fully assembled. The substation is expected to pay more than
Completion of the Fulton Substation is just one part of a planned
Toledo Edison serves more than 300,000 customers in northwestern
|
To quote Larry Kudlow: Free market capitalism is the best path to prosperity! Matters of business and free enterprise are discussed on this blog. Included are company press releases, 3rd party news articles and videos, articles and videos pertaining to small business, and white collar crime.
Search This Blog
Saturday, October 5, 2013
Toledo Edison on Schedule to Complete Fulton Substation
FirstEnergy Press Release:
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.